Transmission Elements Outage Report for  17-Nov-2018
 
A. Details of Transmiss                    ioPlanned Outage n Elements under Planned Outage:-
Sl NoSub-Station/LineCategoryOwner NameOutage DateExpected Revival DateRevival DateReason/Remarks
1NAJAFGARH 220/66kV 100MVA Tx-I220/66kV ICTsDTL24/10/2018 11:5510/12/2018 18:00 OVERHAULING OF TR.
 
B. Details of Transmission Elements under Forced Outa    ge:-Forced Outage
Sl NoSub-Station/LineCategoryOwner NameOutage DateExpected Revival DateRevival DateReason/Remarks
1VASANT KUNJ 220/66kV 160MVA Tx-I220/66kV ICTsDTL26/04/2018 01:4831/12/2018 18:00 TRANSFORMER TRIPPED ON 295B, TROUBLE ALARM, OIL TEMP ALARM, 295CA, 295CC, 195CC, 195CB, TRANSFORMER BURNT DUE TO FIRE.
2NARELA 66/33kV, 30MVA Tx 66/33kV ICTsDTL11/08/2018 18:1830/11/2018 18:0030/11/2018 18:00TR. TRIPPED ON 86, DIFFERENTIAL RELAY. TO BE DE-CAPITALIZED.
3NARELA 66kV 20MVAR CAP. BANK-ICapacitor BanksDTL11/08/2018 18:1830/11/2018 18:00 CAPACITOR BANK CELLS BLASTED, CELLS TO BE REPLACED.
4BAWANA 400/220kV 315MVA ICT-III400/220kV 315MVA ICTDTL02/09/2018 16:2230/11/2018 18:00 TRIPPED ON DIFFERENTIAL, Y PHASE BUSHING DAMAGED, BEING ATTENDED BY PGCIL STAFF.
5RAJGHAT 220/33kV 100MVA Tx-I 220/33kV ICTsDTL03/09/2018 21:5630/11/2018 18:00 TRIPPED ON BUCHLOZ RELAY.
6OKHLA 220/66kV 100MVA Tx-I220/66kV ICTsDTL27/09/2018 10:1530/11/2018 18:00 Y PHASE WINDING DAMAGED. TO BE REPLACED.
C. Details of Transmission Elements Opened manually due t       o H igh Voltage:-