Transmission Elements Outage Report for  24-May-2019
 
A. Details of Transmiss                    ioPlanned Outage n Elements under Planned Outage:-
Sl NoSub-Station/LineCategoryOwner NameOutage DateExpected Revival DateRevival DateReason/Remarks
1GAZIPUR 220/66kV 100MVA Tx-II220/66kV ICTsDTL23/05/2019 21:58 24/05/2019 07:20HOT POINT.
2220 KV GOPALPUR-WAZIRABAD CKT - 1220 KV LINEDTL23/05/2019 21:58 24/05/2019 07:20HOT POINT.
 
B. Details of Transmission Elements under Forced Outa    ge:-Forced Outage
Sl NoSub-Station/LineCategoryOwner NameOutage DateExpected Revival DateRevival DateReason/Remarks
1RAJGHAT 220/33kV 100MVA Tx-I 220/33kV ICTsDTL03/09/2018 21:5631/05/2019 18:00 TRIPPED ON BUCHLOZ RELAY.
2RAJGHAT 220/33kV 100MVA Tx-2 220/33kV ICTsDTL13/05/2019 17:3531/05/2019 18:00 FIRE REPORTED IN CONTROL CABLE TRENCH.
C. Details of Transmission Elements Opened manually due t       o H igh Voltage:-